Western Transport Corridor - Tumkur-Haveri Section of NH-4 - Rehabilitation and Upgrading of Sira to Chitraduga (Km 122.30 to Km 189.00) in the State of Karnataka - Package 2

(Road length = 67.56 Km)

 

Employer

National Highways Authority of India

 

General/Main Contractor

UEM-ESSAR JV

 

Main Sub-contractor

UE Development India Pvt. Ltd.

 

Date of Contract

16 January 2002

 

Date of Commencement

01 March 2002

 

Date of Completion

26 March 2008

 


Project

Four laning and strengthening of existing two lane section between Km 321.10 to Km 393.00 on NH-2 (Construction Package 1-C)

(Road length = 71.90 Km)

 

Employer

National Highways Authority of India

 

General/Main Contractor

PATI-BEL JV

 

Main Sub-contractor

UE Development India Pvt. Ltd.

 

Date of Contract

26 March 2002

 

Date of Commencement

30 March 2002

 

Date of Completion

29 March 2005

 

Project

Strengthening of the existing 4 lanes from Km 28.00 to Km 67.00 and widening of the existing 2 lanes from Km 67.00 to Km 121.00 to 4 lane dual carriageway and strengthening thereof.

 

(Road Length = 93.00 Km)

 

Employer

National Highways Authority of India

 

General/Main Contractor

GMR Tambaram-Tindivanam Expressways Pvt. Ltd.

 

EPC Contractor

UE Development India Pvt. Ltd.

 

Date of Contract

10 January 2002

 

Date of Commencement

08 May 2002

 

Date of Completion

11 October 2004

 


Project

Operation & Maintenance of Km 28.00 to Km 121.00 of Tambaram-Tindivanam Section of NH-45,

(Road length = 93.00 Km)

 

Employer

National Highways Authority of India

 

General/Main Contractor

GRM Tambaram-Tindivanam Expressways Pvt. Ltd.

 

O&M Contractor

UE Development India Pvt. Ltd.

 

Date of Contract

10 January 2002

 

Date of Commencement

24th October 2004

 

Expected Date of Completion

8th Novenber 2019

 


Project

Strengthening of the existing 4 lanes from Km. 300.00 to Km. 359.20 to 4 lane dual carriageway and strengthening thereof.

 

(Road Length = 59.20 Km)

 

Employer

National Highways Authority of India

 

General/Main Contractor

GMR Tuni-Anakapalli Expressways Pvt. Ltd.

 

EPC Contractor

UE Development India Pvt. Ltd.

 

Date of Contract

10 January 2002

 

Date of Commencement

08 May 2002

 

Date of Completion

24 December 2004

 

Project

Operation & Maintenance of Km 300.00 to Km 359.20 of Tuni-Anakapalli Section of NH-5.

 

(Road Length = 59.20 Km)

 

Employer

National Highways Authority of India

 

General/Main Contractor

GMR Tuni-Anakapalli Expressways Pvt. Ltd.

 

O&M Contractor

UE Development India Pvt. Ltd.

 

Date of Contract

10 January 2002

 

Date of Commencement

24 October 2004

 

Expected Date of Completion

 

08 November 2019

 

 

Project

Improvement of roads by widening, strengthening, re-construction/raising, providing drains, widening of bridges/culverts, retaining structures and other miscellaneous works. (Improvement of 4-laning: 5 roads;

New construction of roads: 6 roads)

 

Employer

Haryana State Roads & Bridges Development Corporation Ltd.

 

General/Main Contractor

Niraj Cement Structurals Ltd.

 

Main Sub-contractor

(On back-to-back basis)

 

UE Development India Pvt. Ltd.

 

Date of Contract

15 April 2009

 

Date of Commencement

15 May 2009

 

Expected Date of Completion

August 2011

 

 

 

Project

 

Rehabilitation & up-gradation works from –

Taikkod-Kottarakkara (Km 25.250 – Km 71.272)

Kottarakkara-Chengannur (Km 72.400 – Km 116.830)

Taikkod-NH 47 (Km 0.000 – Km 12.600)

Alappuzha-Chenganasserry (Km 0.000 – Km 24.140)

 

Employer

Kerala State Public Works Department

 

General/Main Contractor

PATI-BEL JV

 

Main Sub-contractor

UE Development India Pvt. Ltd.

 

Date of Original Contract

07 November 2002

 

Date of Commencement

16 December 2002

 

Date of Supplementary Contract

 

12 December 2007

 

Project

Construction of Multi-storied Rehab Building C2 (Building No. 12) & C3 (Building No. 14) of Cluster R-5 at Plot No. CTS NO. 27 (PT), 29(PT) & 30(PT), Golibar Road, Santa Cruz (E), Mumbai.

 

Employer

Shivalik Ventures Pvt. Ltd.

 

General/Main Contractor

UEDI-CANTER B&B JV

 

Main Sub-contractor

 

UE Development India Pvt. Ltd.

 

Date of Contract

12 March 2010

 

Date of Commencement

19 March 2010

 

Expected Date of Completion

June 2011

 

 

 

Project

 

Widening of existing 2 lane carriageway from Shilphata to Kalyan and from existing Toll Plaza to Bhiwandi by-pass junction.

 

(Road length = 21.80 Km)

 

Employer

Maharashtra State Road Development Corporation

 

General/Main Contractor

PLUS BKSP Toll Ltd.

 

Main Sub-contractor

 

UE Development India Pvt. Ltd.

 

Date of Contract

24 November 2006

 

Date of Commencement

24 November 2006

 

Date of Completion

07 March 2008

 

 

 

Project

 

Construction, Execution and Completion of various building and/or engineering works at Sushant Golf City, Lucknow

 

Employer

Ansal Properties & Infrastructure Ltd.

 

General/Main Contractor

UEM Builders-Ansal-API Contracts Pvt. Ltd.

 

Main Sub-contractor/ Project Management Services Provider

 

UE Development India Pvt. Ltd.

 

Date of Contract

 

·        Road Works: 18 April 2008

·        Building Works: 16 June 2010

 

Date of Commencement

·        Road Works: 01 April 2008

·        Building Works: 01 June 2010

 

Expected Date of Completion

·        Road Works: 31 March 2012

·        Building Works: 08 June 2012

 

 

Project

 

Construction of four laning works for Ghaziabad-Aligarh Section of NH-91 from Km 23.60 to Km 62.60 in the State of Uttar Pradesh (Package No. 1, 2 & ROB at Dadri).

 

(Road length = 39.00 Km)

 

Employer

National Highways Authority of India

 

General/Main Contractor

SREI-PNC-Galfar JV

 

EPC Contractor

PNC Infratech Ltd.

 

Sub-contractor

 

UE Development India Pvt. Ltd.

 

Date of Contract

30 August 2010

 

Date of Commencement

29 July 2010

 

Expected Date of Completion

28 July 2012